Week 1:

  • [x] Create a schedule & goals with time frames.
  • [x] Get the LED to blink.

Week 2:

  • [x] Establish project idea by Thursday.
  • [x] Start & Finish Pre-lab. (<1 day - Pooja sent us hers)
  • [x] Investigate how to make the super coiled polymer actuators (SCP)
  • [ ] Reading a LOT of articles & journals - ONGOING assignment
  • [x] Finalize Research. (1 day)

Week 3: (all three goals will go on simultaneously)

  • [x] Start making SCP. (3 days)
  • [_] Program microchip/cellphone. (4 days)
  • [_] Design & test out robot configurations. (4 days)
  • [x] Start abstract & lab report. (2 days)

Week 4:

  • [ ] Finish making SCP actuators. (2 days)
  • [ ] Program microchip/cellphone. (4 days)
  • [ ] Design & test out robot configurations. (4 days)
  • [ ] Begin testing & revising. (4 days)
  • [ ] If testing is successful of individual parts, then begin overall integration & assembly. (3 days)
  • [ ] Revise abstract & lab report. (2 days)

Week 5:

  • [ ] Continue testing & analyzing data. (3 days)
  • [ ] Make graphs. (1 day)
  • [ ] Continue abstract & lab report. (2 days)
  • [ ] Start poster. (3 days)

Week 6:

  • [ ] Finish abstract & lab report. (5 days)
  • [ ] Finalize testing & data. (5 days)

Week 7:

  • [ ] Finsh poster.
  • [ ] Develop presentation.
  • [ ] Investigate further possible applications of our project

Week 8:

  • Finish presentation